14
Installation Checklist
A. Water Heater Location
B. Water Supply
C. Gas Supply
❑ Water heater securely anchored.
❑ Indoors and protected from freezing
temperatures.
❑ Proper clearance from combustible
surfaces observed and water heater not
installed on carpeted floor.
❑ Sufficient fresh air supply for proper
operation of water heater.
❑ Air supply free of corrosive elements
and flammable vapors.
❑ Provisions made to protect area from
water damage.
❑ Sufficient room to service heater.
❑ Combustible materials, such as clothing,
cleaning materials, rags, etc. clear of the
base of the heater.
❑ Clearances from combustion air inlet
openings observed (see page 7).
❑ Water heater completely filled with
water.
❑ Air purged from water heater and
piping.
❑ Water connections tight and free of
leaks.
❑ Gas line equipped with shut-off valve,
union and sediment trap.
❑ Approved pipe joint compound used.
❑ Soap and water solution used to check
all connections and fittings for possible
gas leak.
❑ Gas Company inspected installation (if
required).
❑
After conversion, be certain the gas
supplied to the heater is the type the
valve has been converted for (LP
for heaters converted to LP use, and
natural gas for heaters converted to
natural gas use)
.
D. Relief Valve
❑ Temperature and Pressure Relief Valve
properly installed and discharge line run
to open drain.
❑ Discharge line protected from freezing.
E. Venting
❑ Flue baffle properly hung in top of
heater’s flue.
❑ Draft hood properly installed.
❑ Gas Vent Roof Jack properly installed.